PMP – Activity 10B
Using the following information:
- Build a network diagram
- Identify the early start, early finish, late start late finish for each activity
- Identify the critical path
- Identify the duration of the critical path
- What is the float of Activity B
- What is the float of Activity H

Having Trouble Meeting Your Deadline?
Get your assignment on PMP – Activity 10B completed on time. avoid delay and – ORDER NOW
Activity Predecessor Duration in Days
A Start 3
B Start 6
c A, B 12
D B 5
E D 4
F C 6
G E,F 8
H E 7
I H 3