As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and projects running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.
As the project manager, you have been asked to create an initial project schedule for a project known as the "Technology Refresh Project." The prior project manager assembled the project information and put it onto a spreadsheet. Based on this information, you are to create an initial project schedule using Microsoft Project.

Having Trouble Meeting Your Deadline?
Get your assignment on Wk 3 completed on time. avoid delay and – ORDER NOW
Open the attached document Topic 2 Project Durations TEMPLATE (a Microsoft Excel file). You will notice a series of project tasks; optimistic, most likely, and pessimistic durations for each lowest-level task; and predecessor information. Do not alter this information.
In the "PERT Expected Duration (days)" column, calculate the PERT Expected Duration for each lowest-level task. Round the duration entries to the nearest integer.
Open the attached document Topic 2 Initial Project Schedule TEMPLATE (a Microsoft Project file).
Enter the tasks shown in Topic 2 Project Durations TEMPLATE (a Microsoft Excel file) into Topic 2, Initial Project Schedule TEMPLATE (a Microsoft Project file).
Based on the task hierarchy in Topic 2 Project Durations TEMPLATE (a Microsoft Excel file), demote the appropriate tasks using the green indent and outdent arrows in the TASK Ribbon, SCHEDULE group. Notice how the WBS field is automatically updated as tasks are indented and outdented. Be sure that your Microsoft Project task hierarchy exactly matches the task hierarchy in "Topic 2 Project Durations TEMPLATE" (a Microsoft Excel file).
Based on your computed PERT Expected Durations from above, enter these durations in the "Duration" field in the Microsoft Project file. Note the following:
- Be sure that you do not directly enter durations into Microsoft Project summary tasks (i.e., the bold tasks). Note that the Microsoft Project summary task durations and dates are automatically updated as durations are entered into the lowest-level tasks.
- Be sure that lowest-level task durations are entered as whole numbers.
Based on the predecessor information in Topic 2, Project Durations TEMPLATE Microsoft Excel file, update the "Predecessor" column in Topic 2 Initial Project Schedule TEMPLATE (a Microsoft Project file). Note the following:
- The "Successor" column updates automatically, as predecessors are entered. Thus there is no need to enter any information in the Successor column.
- Be sure that the summary tasks (i.e., the bold tasks) do not contain predecessors or successors. Predecessors and successors are only entered at the lowest-level task level.
- Ensure that lowest-level tasks have at least one predecessor (except the first task) and at least one successor (except the last task).
Display the critical path. Go to the FORMAT ribbon and check the "Critical Tasks" box in the BAR STYLES group. Note that the critical path task bars will turn red. Also, take note that the Total Slack column contains 0 days for the critical path tasks.
Durations Template
| Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Weighed Average Duration (days) |
| Initiating | ||||
| Finalize project team | 2 | 4 | 10 | |
| Develop project charter | 2 | 3 | 13 | |
| Planning | ||||
| Develop scope statement | 4 | 8 | 14 | |
| Develop and refine other plans | 10 | 20 | 29 | |
| Executing | ||||
| Concept | ||||
| Evaluate current systems | 2 | 4 | 10 | |
| Define requirements | 4 | 16 | 22 | |
| Define user requirements | 8 | 10 | 23 | |
| Define content requirements | 4 | 16 | 29 | |
| Define system requirements | 7 | 17 | 33 | |
| Define server owner requirements | 4 | 18 | 20 | |
| Define specific functionality | 10 | 20 | 33 | |
| Define risks and risk management approach | 5 | 13 | 21 | |
| Develop project plan | 9 | 18 | 32 | |
| Brief web development team | 1 | 1 | 2 | |
| Web Site Design | ||||
| Design registration for recreational programs | 4 | 16 | 22 | |
| Design registration for classes and programs | 7 | 19 | 33 | |
| Design tracking system | 8 | 10 | 27 | |
| Design incentive system | 10 | 15 | 22 | |
| Web Site Development | ||||
| Develop registration for recreational programs | 9 | 22 | 32 | |
| Develop registration for classes and programs | 12 | 21 | 37 | |
| Develop tracking system | 5 | 17 | 21 | |
| Develop incentive system | 4 | 13 | 20 | |
| Conduct Verification Testing | 9 | 18 | 27 | |
| Conduct Validation Testing | 4 | 15 | 20 | |
| Conduct Pilot Testing | 2 | 3 | 9 | |
| Roll Out | ||||
| Move site to production server | 2 | 3 | 6 | |
| Determine roll out schedule | 2 | 3 | 5 | |
| Communicate roll out plan to users | 1 | 1 | 2 | |
| Conduct user training | 2 | 4 | 12 | |
| Deploy system | 1 | 1 | 2 | |
| Support | ||||
| Determine what support resources are needed | 2 | 3 | 4 | |
| Make appropriate staffing changes | 2 | 3 | 4 | |
| Determine method that users will attain support | 2 | 3 | 5 | |
| Determine support process | 2 | 5 | 11 | |
| Launch support | 1 | 1 | 2 | |
| Controlling | ||||
| Hold formal customer review | 1 | 1 | 2 | |
| Closing | ||||
| Prepare final report and presentation | 2 | 5 | 10 | |
| Deliver final report and presentation | 1 | 1 | 2 |
Durations Solution
| ID | Task | Optimistic Duration (days) | Most Likely Duration (days) | Pessimistic Duration (days) | PERT Expected Duration (days) | Predecessor(s) (ID) |
| 1 | TECHNOLOGY REFRESH PROJECT | |||||
| 2 | Initiating | |||||
| 3 | Meet with key stakeholders | 1 | 2 | 3 | ||
| 4 | Finalize statement of work | 3 | 5 | 9 | 3 | |
| 5 | Secure project team leads | 3 | 5 | 13 | 3 | |
| 6 | Finalize stakeholder register | 2 | 4 | 7 | 5 | |
| 7 | Develop project charter | 10 | 16 | 24 | 3 | |
| 8 | Finalize project charter | 1 | 2 | 4 | 4,7 | |
| 9 | Planning | |||||
| 10 | Scope Planning | |||||
| 11 | Requirements | |||||
| 12 | Develop/finalize functional requirements | 5 | 16 | 24 | 4 | |
| 13 | Develop/finalize hardware requirements | 5 | 12 | 20 | 12 | |
| 14 | Develop/finalize software requirements | 5 | 10 | 14 | 12 | |
| 15 | Develop/finalize requirements traceability matrix | 4 | 9 | 17 | 12,13,14 | |
| 16 | Finalize project deliverables | 2 | 2 | 3 | 15,8 | |
| 17 | Develop scope statement | 4 | 6 | 16 | 16 | |
| 18 | Finalize/Update WBS | 2 | 3 | 8 | 17 | |
| 19 | Schedule (Time) and Cost Planning | |||||
| 20 | Finalize hardware/software costs | 6 | 12 | 18 | 13,14 | |
| 21 | Update activities and duration estimates | 2 | 10 | 18 | 18,20 | |
| 22 | Human Resource Planning | |||||
| 23 | Finalize resource requirements | 4 | 8 | 19 | 21 | |
| 24 | Finalize project costs | 4 | 6 | 12 | 21,23 | |
| 25 | Identify training requirements | 2 | 4 | 5 | 23 | |
| 26 | Complete training activities | 6 | 12 | 14 | 25 | |
| 27 | Quality Planning | |||||
| 28 | Determine impacted quality processes | 2 | 3 | 4 | 15 | |
| 29 | Finalize quality management plan | 2 | 6 | 8 | 28,23 | |
| 30 | Risk Planning | |||||
| 31 | Update project risks | 10 | 10 | 18 | 23 | |
| 32 | Draft risk register | 2 | 3 | 4 | 31 | |
| 33 | Finalize risk management plan | 2 | 3 | 4 | 32 | |
| 34 | Finalize Project Plan | |||||
| 35 | Finalize communications management plan | 2 | 3 | 4 | 23 | |
| 36 | Finalize procurement management plan | 2 | 10 | 12 | 16 | |
| 37 | Finalize stakeholder management plan | 2 | 2 | 2 | 6,23 | |
| 38 | Finalize project schedule/cost baseline | 2 | 10 | 18 | 24 | |
| 39 | Finalize project plan | 2 | 5 | 16 | 29,36,35,37,38 | |
| 40 | Obtain approval for project plan | 2 | 4 | 10 | 33,39 | |
| 41 | Executing | |||||
| 42 | Hardware | |||||
| 43 | Procure hardware from suppliers | 8 | 10 | 22 | 36 | |
| 44 | Software | |||||
| 45 | Obtain software OS licenses | 6 | 12 | 20 | 36 | |
| 46 | Obtain software application licenses | 6 | 12 | 20 | 36 | |
| 47 | Pilot Testing | |||||
| 48 | Setup test area | 2 | 3 | 4 | 40 | |
| 49 | Load software onto pilot machines | 5 | 2 | 3 | 45,46,48,43 | |
| 50 | Validate functionality | 3 | 5 | 9 | 49 | |
| 51 | Deployment | |||||
| 52 | Configure production hardware | 10 | 18 | 28 | 26,50,67,63 | |
| 53 | Deploy production hardware | 12 | 16 | 18 | 52 | |
| 54 | Load software to deployed hardware | 10 | 16 | 30 | 53 | |
| 55 | Testing | |||||
| 56 | Validate startup on deployed hardware | 4 | 6 | 10 | 54 | |
| 57 | Perform OS testing | 4 | 8 | 10 | 56 | |
| 58 | Perform application testing | 4 | 13 | 18 | 57 | |
| 59 | Obtain formal sign-off from users | 6 | 14 | 22 | 58 | |
| 60 | Monitoring and Controlling | |||||
| 61 | Formal Customer Review 1 | |||||
| 62 | Hold formal customer review after project plan approval | 1 | 2 | 2 | 40 | |
| 63 | Update project plan | 4 | 8 | 10 | 62 | |
| 64 | Formal Customer Review 2 | |||||
| 65 | Obtain updates regarding key deliverables from project team | 6 | 12 | 18 | 50 | |
| 66 | Hold formal customer review after pilot testing | 1 | 2 | 2 | 50,65 | |
| 67 | Update project plan | 4 | 8 | 10 | 66 | |
| 68 | Closing | |||||
| 69 | External | |||||
| 70 | Finalize procurement with suppliers | 5 | 12 | 23 | 59 | |
| 71 | Customer Approval | |||||
| 72 | Hold final customer review | 1 | 2 | 2 | 59 | |
| 73 | Prepare/submit final customer report | 4 | 6 | 8 | 59 | |
| 74 | Audit against contractual deliverables | 3 | 6 | 8 | 72,73 | |
| 75 | Obtain final customer approval | 2 | 3 | 4 | 74 | |
| 76 | Internal | |||||
| 77 | Hold lessons learned meeting | 1 | 1 | 1 | 75,70 | |
| 78 | Update final internal report | 4 | 6 | 8 | 77 | |
| 79 | Hold project team celebration event | 1 | 1 | 1 | 78 |